Car plastic bumper coating line design process
Time:2012-10-22 11:47:46

       The car bumper is the car important exterior decoration part, along with the car coating request unceasing enhancement, the bumper coating also more and more receives each specialized factory's attention. Car bumper mainly adopts plastic material, coating on the surface is difficult to attach, and low thermal deformation temperature of the plastic parts, generally in use in the production of paint drying temperature is lower than the drying temperature of the coating used of the metal, so the plastic coating and metal coating are quite different in process and coating materials, bumper painting with car coating commonly mixed production line. At present, some large domestic automobile manufacturers have taken the injection molding and painting of the bumper as an important part of vehicle production, and built the injection molding and painting workshop of the bumper when planning the new factory. For example, Toyota has built a resin workshop (namely the injection molding and painting workshop of the bumper and other plastic parts) in the domestic construction factory. The bumper of some automobile factories in China is provided by the large-scale professional plastic parts processing factory, and the large-scale automobile plastic parts production factories in China include Jiangyin molding and Shanghai Yanfeng Weistong, etc.


       The design of a number of bumper coating lines in China has absorbed the experience and technology of Japan, South Korea, Europe and The United States, etc. These coating lines have many different places in the process, equipment layout and mechanized form. In order to reduce the processing cost of plastic bumpers and improve their coating quality, a lot of researches have been made on coating materials, coating process and coating equipment, etc., and some achievements have been made. Therefore, the coating line design has undergone great changes in recent years.


1. Overall layout of coating line

       The overall arrangement of large coating lines tends to be regionalized and three-dimensional. The same or similar equipment and processes should be arranged in the same area as far as possible to facilitate the organization and management of production. The first floor is mainly equipped with upper and lower parts, pre-treatment, polishing, inspection, decoration and auxiliary equipment; The second floor is mainly equipped with spray painting room, drying room and air conditioning platform area. This three-dimensional arrangement of equipment is more conducive to improve the cleanliness of the spraying clean area, which is of great help to improve the qualification rate of the products off the production line at one time. The whole coating workshop is fully enclosed workshop, artificial all standing in line at the upper and lower parts of the unilateral operation, bumper painting takes the form of automatic spraying combined with artificial spray, spray paint room concentrated air exhaust emissions or dust emission concentration after burning, for centralized paint system for paint combined with line and small system for the model.


2 Coating materials

       Plastic bumper heat resistance is poor, when high temperature easy deformation, so the bumper coating generally cannot choose drying temperature is too high coating, drying temperature is about 80±5℃ and 120±5℃ for domestic paint. The bumper coating is composite coating namely primer + color paint + varnish, primer has two components and one component two, color paint mostly USES one component paint, varnish mostly USES two components paint. The two-component primer has a better covering force after baking, and can polish the surface particles and other paint defects, especially suitable for the appearance of the plastic parts are poor, but the two-component primer under the wet film state of electrical conductivity is generally poor, such as the primer is not dried spraying paint will affect the adhesion of color paint. Two - component varnish wide construction range, compared with one - component varnish, with less pollution, easy to adjust the advantages. The application of two-component primer and varnish system has disadvantages such as large equipment investment and complex maintenance of paint conveying pipeline, but the paint itself is easy to be adjusted, and it is easy to obtain a good surface condition of paint film.


       The 3C1B process can save the one-time investment of equipment and the operating cost of equipment in the later stage. The existing plastic bumper coating line with large production capacity in China adopts this process form and has been put into mass production with relatively stable operation. Considering 3 c1b coating process in the domestic application in coating production line design is less, and 3 c1b technology in coating construction parameter control, coating field management, coating performance pledge, a referral qualified rate of products, as well as a certain risk, mostly European and American automobile manufacturers at the same time the required 3 c2b technology on bumper painting, so some coating production line in domestic press 3 c2b process design and construction at the same time also can achieve 3 c1b technology forms.


3.2 prior to processing

       The pretreatment of the plastic bumper before painting is mainly to remove the dust, oil and residual release agent on the surface of the workpiece, and at the same time to activate the surface. Poor pretreatment can lead to poor adhesion, shrinkage cavity and particle defects. There are two forms of pretreatment, one is automatic spraying, the other is manual wiping. Automatic spraying is to hang the workpiece on the conveying equipment through the pretreatment spray line, the main process is: pre-degreasing → degreasing → washing 1→ washing 2→ fresh DI washing → water blowing → moisture drying → strong cold; Manual wipe is mainly used to wipe the whole workpiece surface manually with solvent, which can reduce the one-time investment of equipment and its operating cost. Domestic large quantities of plastic bumper coating line mostly adopts automatic spraying, small quantities of bumper coating and small parts coating mostly adopts manual wiping method.


3.3 Flame treatment

       The flame treatment further activates the workpiece surface. The robot jets flames to the surface of the workpiece. Manual and automatic electrostatic removal procedures are set after the flame treatment process to enhance the binding force between the workpiece and the coating film.


3.4 on the cover

       On the screen is mainly on the surface of the workpiece some do not need to be sprayed on the area to cover processing, the general line more difficult to cover, using more line shielding.


3.5 spray paint

       Workpiece spraying mostly adopts the combination of robot automatic spraying and artificial spraying, first automatic spraying, and then manual inspection of supplementary spraying. Some production lines can be completely automatic spraying after commissioning and enter into mass production. Automatic painting mainly adopts robot spraying. Generally, air spray gun is used for primer, cup rotary workstation + spray gun workstation is used for color paint and spray gun + cup workstation is used for varnish 2 workstations.


4 Coating equipment

       The equipment of plastic bumper coating line mainly includes mechanical conveying equipment, pretreatment equipment, flame treatment equipment, spray painting room equipment, drying furnace and artificial working area equipment, etc.


4.1 Mechanical conveying equipment

       Plastic bumper spraying line mechanized conveyor equipment in the form of more, there are general suspension conveyor chain, reverse cumulative chain and skid transport form. Skid transport layout is flexible and changeable. In recent years, many production lines built in China have adopted skid transport, while Japanese bumper coating line mainly adopts reverse cumulative chain. Considering that some equipment of the pretreatment process conveying system has the requirements of waterproofing and anti-rot and the influence of drying process temperature, the driving device of the skid conveyor system in the general pretreatment and drying process adopts the external type.


4.2 Pre-processing equipment

       The pretreatment equipment mainly includes non-standard equipment, circulation system and exhaust system. The degreasing liquid of plastic bumper is slightly acidic (pH value is generally around 6.4), which is different from the degreasing liquid of car body, so the pre-treatment equipment should consider acid resistance, it is recommended that the pre-treatment closed chamber body and tank body adopt stainless steel material. The top of the pre-treatment equipment room is equipped with an exhaust fan to avoid the gas diffusion to the outside of the room. It is suggested that a maintenance platform, a maintenance door and a cantilever searchlight be installed on one side of the pre-treatment room to facilitate the maintenance and repair of the equipment.


3 Coating process

       3.1 Main process forms of coating line

       Commonly used coating process for: plastic bumper on a - before treatment - water on the dry and cold - flame treatment - covered - in addition to static electricity - spray primer - flow flat - primer to dry and cold - primer inspection/ground - in addition to static electricity - spray paint to flow flat - spray varnish - flow flat, paint to dry and cold - inspection - under a - defects repair. The above process flow is three spray and two bake (3C2B) process, and there is also a three spray and one bake (3C1B) painting process (the process of "removing static electricity" after the "primer drying" to the primer in the above process flow is cancelled).


4.3 spray room

       The existing domestic painting production line of the spray painting room has The Van Winkle spray painting room, the water spin spray painting room and the water curtain type spray painting room and so on, now USES the Van Winkle spray painting room. There are two kinds of air supply and exhaust system in spray booth: fresh air and circulating air. The all-fresh air mode is that the air supply air conditioning unit in the spray chamber takes air from the outside of the chamber and sends it to the spray chamber after multi-stage treatment of the air conditioning unit. After the air is utilized in the spray chamber, the exhaust fan in the spray chamber is all discharged into the atmosphere. The circulating air mode is the air circulation utilization in the spray painting room (namely, the air enters the spray painting room through the air supply air conditioner, and then returns to the air supply air conditioner through the circulating air treatment equipment for reuse). The air exhaust in the spray painting room is not all discharged, only part of the discharge and part of the supplement. The amount of air supply and exhaust shall be calculated according to the balance of air flow in the spray chamber, the limit concentration of exhaust gas explosion in the spray chamber and the requirements of paint performance. Some production lines are designed to supplement the air flow with 10%, 30% of the total circulation air flow. The air volume of spray chamber exhaust and fill air should not be too low, too low will lead to the circulation of the wind organic solvent content is too high, easy to cause paint film surface gloss, and spray construction parameters control is more difficult. The concentration of exhaust gas in the spray chamber with circulating air is high (exceeding the requirements of national environmental protection standards), and the exhaust gas shall be incinerated back into the atmosphere (the exhaust gas after incineration can meet the national environmental protection requirements). The temperature of the painting room is generally required to be controlled at about 23℃, heat exchange in winter, refrigeration in summer, the use of fresh air coating production line energy consumption is large. The use of circulating air conditioning can reduce the energy consumption of production line (comprehensive energy consumption can be reduced by more than 30%, the installed power of related equipment can be reduced by 40%), and save the operating cost. Spray chamber adopts circulation air supply, corresponding spraying form should adopt automatic spraying, because the circulation air harmful gas content is high, not suitable for manual operation, such as artificial spraying should wear clothing and masks with anti-gas function.


4.4 drying furnace

       Baking furnace are mainly in the form of straight through, bridge and П type 3 kinds. The mechanical conveying of Japanese coating production line mostly adopts the form of reverse cumulative chain, and the drying furnace is the bridge drying furnace. Europe and the United States system using light skid transportation system, drying furnace for drying furnace П type. Double stroke drying oven is used to reduce heat dissipation area and energy consumption.


4.5 Paint supply system

       There are two paint systems, one is the centralized paint system, that is, all the paint is concentrated in a specific area for deployment, the centralized paint system to be arranged in the distance of three paint rooms near the place, to reduce the paint pipe passing long caused by the pressure loss and temperature loss, and avoid the pipeline cleaning difficulties; The other is the line edge system, that is, the paint transfer equipment is placed near the spray chamber. The volume of paint supplying tank used by the line-edge system is relatively concentrated, so the line-edge system is also known as the small system. The advantage of the small system is that it can meet the spraying production under the condition of small paint feeding. It can be used for infrequent production of color paint, new color trial production and temporary adjustment of color coating. A centralized paint system is used for primers, varnishes, and several high volume paints.


5 conclusion

       Countries to work more and more attention to environmental protection, the state environmental protection administration has issued the relevant standard of clean production, coating line will be more and more strict emissions, car coating production line has been developed to the direction of water paint, bumper painting is also bound to develop in the direction of the water-based coating, the domestic has been bumper painting line using water-based paint coating.

Service hotline

020-36860788

WeChat

Feedback

Feedback

国产在线视频不卡 | 色哟哟国产 | 你懂的成人 | 图片区 小说区 区 亚洲五月 | 国产91精品ai换脸 | 色婷婷视频在线观看 | 好吊色网站 | 开心春色激情网 | 欧美激情网站 | 伊人影院在线播放 | 51自拍视频 | 开心激情播播 | 国语对白清晰刺激对白 | 国产精品ww | 久久亚 | 蜜臀av在线观看 | 久久久久无码国产精品一区李宗瑞 | 欧美久久一区二区 | 美梦视频大全在线观看高清 | 国产中文字幕在线观看 | 国产乱乱| 免费av高清| 女~淫辱の触手3d动漫 | 在线观看国产一区 | www欧美色| 欧美成人一区二区三区片免费 | 精品视频一区二区在线观看 | 美丽的小蜜桃2:美丽人生 | 精品国产一区二区三区在线观看 | 激情婷婷六月天 | 中文字幕一区二区三区四区视频 | www日本色 | 女人天堂网 | 久久视频免费在线观看 | 一区二区国产精品视频 | 婷婷开心激情 | 亚洲成人一二三 | 欧美精品乱码视频一二专区 | 香蕉尹人 | 找av123导航| 亚洲GV成人无码久久精品 | 亚洲国产中文字幕在线观看 | 亚洲在线一区二区 | av在线播放地址 | 三级黄色片网站 | 日日天天 | 日韩久久精品视频 | 啪啪一级片 | 国产成人免费网站 | 91免费国产视频 | 欧美操大逼 | 伊人亚洲综合 | 亚洲第五页 | 自拍偷拍亚洲欧美 | 美女av一区 | 综合久色 | 一级大毛片 | 18深夜在线观看免费视频 | 三级成人网 | 日韩精品视频免费播放 | 日韩av福利| 男女无遮挡免费视频 | 国产做爰高潮呻吟视频 | 日本免费在线观看视频 | videosex抽搐痉挛高潮 | 日本欧美一区二区三区 | 日韩新片王网 | 国产午夜精品一区二区 | 日本成人免费视频 | 韩国黄色大片 | 一级黄色短视频 | 日韩国产在线播放 | 男男捆绑取精gay呻吟 | 色欲久久久天天天综合网 | 亚洲欧美日韩国产一区 | 婷婷资源网| 国产午夜片 | 国产第一亚洲 | 欧美另类xxx | 天天干夜夜夜 | 亚洲一区二区三区乱码 | 免费三级网站 | 特级淫片aaaaaaa级 | 99精品一级欧美片免费播放 | 国产精品扒开腿做爽爽爽视频 | 日日操夜夜操天天操 | 亚洲精品无码久久久久久久 | 俺也去网站 | 你懂的在线免费观看 | 在线免费观看亚洲 | av高清在线观看 | 午夜久久乐 | 91免费福利 | 日本亚洲视频 | 日韩在线天堂 | 奇米在线777| 又色又爽又黄18网站 | 中文字幕人妻一区二区三区 | 噜噜噜av| 你懂得视频在线观看 | 天海翼av在线 | 男女av免费 | 国产精品美女久久久久av超清 | 中文字字幕在线中文乱码 | 韩国精品在线观看 | 夜夜爱av | 中文字幕理伦片免费看 | 肉丝美脚视频一区二区 | 岛国av不卡| 痴汉电车在线播放 | 色噜噜狠狠一区二区三区果冻 | 欧美激情在线看 | 18av在线播放 | 99色精品 | av日韩中文字幕 | 国产尤物在线观看 | 亚洲午夜精品 | 国产视频成人 | 欧美激情在线一区 | 强迫凌虐淫辱の牝奴在线观看 | 国语对白做受欧美 | 日本网站免费观看 | 国产午夜精品在线观看 | 日韩欧美一级大片 | 手机在线成人 | 五月亚洲 | 男生捅女生肌肌 | 两个人看的www视频免费完整版 | 激情999| 97在线观看免费高清 | 熟妇女人妻丰满少妇中文字幕 | 波多野结衣办公室双飞 | 国产精品污视频 | 午夜电影免费看 | 日韩精品一区二 | 夫妻啪啪呻吟x一88av | 神马午夜888| 五月天国产 | 天天躁日日躁aaaa视频 | 国产一二三四在线 | 他趴在我两腿中间添得好爽在线看 | 9999久久久久| 欧美国产中文字幕 | 嫩草懂你| 日韩欧美国产一区二区 | 亚洲欧美日韩在线 | 国产精品性 | 99热这里只有精品99 | 国产午夜在线 | 伊人免费| 国产一区二区女内射 | 荒岛淫众女h文小说 | 日韩一级二级 | 久久久久999| 天天干天天操天天操 | 午夜影视网 | 国产精品一区二区免费看 | 亚洲免费福利 | 日韩精品一区二区在线播放 | 永久看看免费大片 | 亚洲影音先锋 | 亚洲精久久 | 久久黄视频 | 蜜桃视频成人 | 操操干干 | 美脚の诱脚舐め脚视频播放 | 你懂的网址在线 | 日本在线免费播放 | 91超碰免费在线 | 黄色1级片 | 日本天天操 | 特级西西444www大精品视频 | 亚洲天堂午夜 | 大粗鳮巴久久久久久久久 | 天天色棕合合合合合合合 | 肥臀熟女一区二区三区 | 天天干天天干天天干 | 波多野结衣电影免费观看 | 日韩欧美三区 | 日韩夜夜高潮夜夜爽无码 | 超级乱淫视频 | 亚洲最大的成人网 | 午夜成人免费视频 | 深夜视频网站 | 免费网站在线高清观看 | 亚洲一区二区观看 | 懂色av懂色av粉嫩av分享吧 | av黄色小说 | 风韵丰满熟妇啪啪区老熟熟女 | 成人小视频在线 | 黄网免费在线观看 | 国产女人18毛片水真多1 | 香蕉视频一区二区三区 | 成人亚洲在线 | 国产内射老熟女aaaa∵ | 国产精品九九九九 | 国产少妇自拍 | 深夜成人福利 | 国产一区二区三区网站 | 97中文字幕在线观看 | 欧美二区三区 | 精品无码在线观看 | 欧美三级午夜理伦 | 看av在线 | 免费黄色大片 | 日韩视频在线观看 | 免费观看国产视频 | 爽爽爽网站 | 欧美日韩图片 | 无码精品人妻一区二区三区漫画 | 国内毛片毛片毛片 | 欧美高清性 | 青青草成人在线观看 | 亚洲欧美高清 | 快色视频| 国产午夜精品一区 | 蘑菇福利视频一区播放 | 99热只有这里有精品 | 天天干女人| 黄色一类片| 国产二级片| 麻豆av网 | 国产中文字幕在线观看 | 99国产精品久久久久久久 | 亚洲最大在线 | 天天射寡妇 | 久久中文字幕在线 | 欧美无砖砖区免费 | 成人欧美视频 | 亚洲aaaaaa| 国产老肥熟 | 欧美午夜视频在线观看 | 国产国产国产 | 日韩欧美国产成人 | 亚洲无人禁区 | xxx久久久| 日韩黄色片 | 最新毛片基地 | 干干干日日日 | 亚洲一区二区在线播放 | 免费午夜av| 欧美日本韩国在线 | 亚洲精品在线视频 | 日日摸夜夜爽 | 久久爱伊人 | 国产欧美在线看 | 亚洲精品一区在线 | 蜜桃成人无码区免费视频网站 | 亚洲av成人精品日韩在线播放 | 久热精品视频在线观看 | 韩国黄色片网站 | 国产伦精品一区二区三毛 | 亚洲婷婷在线 | 桃谷绘里香在线观看 | 日韩国产欧美精品 | 99久久99久久免费精品蜜臀 | 催眠美妇肉奴系统 | 日本一区二区免费看 | 亚洲无码精品在线播放 | 国产91九色| 国产九色在线播放九色 | loveme动漫在线观看完整版 | 欧美极品xxxx | 精品在线免费观看视频 | 国产丰满大乳奶水在线视频 | 奇米影视777四色 | 欧美成人一区二区三区高清 | 亚洲aⅴ在线 | 日韩精品一区二区三 | 臭脚猛1s民工调教奴粗口视频 | 色网站在线播放 | 91视频高清 | 欧美色炮 | 国产伦理在线 | 波多野结衣绝顶大高潮 | 亚洲永久免费 | 欧美jizz18性欧美 | 免费激情视频网站 | 69视频网| 久久国产精品波多野结衣 | 日韩黄色免费电影 | 九九精品免费视频 | 免费黄色一级片 | 国产精品一二三 | 亚洲精品福利在线 | 在线观看成年人视频 | 欧美一级免费大片 | 欧美中文在线观看 | 久久精品国产免费 | 制服丝袜影音 | 日韩乱码一区二区 | 欧美日韩一区二区区别是什么 | 国产欧美一区二区三区鸳鸯浴 | 天天碰天天操 | 色www亚洲国产张柏芝 | 天美麻花果冻视频大全英文版 | 色狠狠一区二区三区 | 最好看的mv中文字幕国语电影 | 欧美另类综合 | av大片在线免费观看 | 99re这里都是精品 | 亚洲成人精品一区 | 日韩aaaaaa | 尹人综合网| 欧美18—19性高清hd4k | 亚洲最大福利网站 | 日本一区不卡视频 | 国产在线视频你懂的 | 亚洲欧美在线播放 | 打屁股网址 | 天天躁日日躁狠狠躁av麻豆 | av一级片| 欧美人与动物xxx | 亚洲色图欧美另类 | missav | 免费高清av在线看 | 久久看片网 | 精品日韩一区二区 | 久久波多野结衣 | 亚洲免费大全 | 精品少妇视频 | 日批网址 | 男女爱爱网站 | 日本熟妇一区二区 | 97人人超 | 国产日产亚洲系列最新 | 91国产免费视频 | 黄页免费观看 | 午夜看片 | 影音先锋在线观看视频 | 欧美精品一区二区三区四区 | 捆绑体育生直男榨精呻吟 | av免费在线电影 | 男人的天堂va | 欧美激情视频一区二区三区 | 复古经典毛茸茸xxxxxxxx | a在线观看免费 | 90岁肥老奶奶毛毛外套 | 在线观看视频一区二区 | 黄色大片在线 | 成人免费网站 |